Timeline
- Predesign phase complete
- Schematic Design phase complete
- Design Development phase complete
- Construction Documents/Permitting phase complete
- Bid and Award phase complete
- Construction in progress
- School opened Sept. 6, 2023
Recent Progress
Progress updates are posted for the previous month.
Major activity in January 2024
- Punchlist items are in progress.
Major activity planned for February 2024
- Complete site activities.
- Complete remaining interior finishes and exterior site punchlist items.
Project Photos
Project Designs
Architects drawings of the future school building
About the Project
The existing Viewlands Elementary will be demolished to make way for a new multi-story school building. The new school will be approximately 106,000 square feet and provide permanent classroom space for up to 650 students.
The new Viewlands Elementary School is designed to provide an equitable, safe, and inspired learning environment. A collaborative design process included school leadership, parents, and community members. The resulting plan is infused with nature, outdoor learning, and natural light. It will provide the spaces and resources that students need for academic success.
Outdoor learning areas include adjacent storage, water, and power to support educational activities. Exceptional trees will be preserved, and new trees will increase the overall tree canopy on site when mature.
Secure, enclosed and covered bike parking is located along the main entry route and is visible and accessible to all students and staff. Additional covered, short term bicycle parking for visitors is provided within view of the school’s main office. Site improvements will include covered and open play areas, and new parking.
The school building is thoughtfully designed to fit into the neighborhood and to recognize its unique location adjoining Carkeek Park.
Sustainable Design and Construction
Mechanical and electrical sustainable design features mean that no fossil fuels will be used onsite in accordance with the Board’s Clean Energy Resolution 20/21-18 and will position the school to meet the district’s goal of net-zero energy-usage.
The new school includes a geothermal heating system, a highly efficient ventilation system that recovers 90% of the exhaust air heat, and energy efficient LED lighting. The roof is designed to accommodate solar panels which could offset 80% of the buildings energy use in the future.
Sustainable site design strategies include:
- On-site storm water management with pervious paving and run-off directed to bioretention gardens planted with native plants
- Drought-resistant plantings
- Fully shielded dark-sky compliant site lighting
- Optimal building orientation for maximum daylighting and minimum solar heat gain and glare, which reduces electric lighting use and cooling needs
- Highly insulated walls and roof to increase thermal efficiency
- Fiberglass high-efficiency windows to increase thermal efficiency, reduce air leakage, and minimize outside noise
Projected Energy Use Index (EUI): 15.8
Design Firm: Mahlum Architects
Contractor: Absher Construction
Project manager: Brian Fabella, brfabella@lgmobilereg.com, 206-252-0702
Project Budget: $88.1M
Funding Source: Building Excellence V Capital Levy (BEX V) approved by Seattle voters in 2019